How to measure
- Measure the pour exactly as you would for the Concrete Calculator: length, width and thickness for a slab, diameter and depth for holes.
- Call a ready-mix plant for the price per cubic yard and ask about the minimum order and short-load fee.
- Check the shelf price of the bag size you'd use — 80 lb bags are usually the cheapest per cubic foot.
How the concrete cost calculation works
Volume with waste = shape volume × (1 + waste) Ready-mix order = volume rounded up to ¼ yd Ready-mix cost = order × price per yd + delivery / short-load fee Bag cost = bags × price per bag
Plants sell in quarter-yard steps, so the order rounds up before pricing. Small orders usually carry a short-load fee that can outweigh the concrete itself — enter it so the comparison is fair.
Bags are counted from their published yield (0.60 cu ft per 80 lb bag) and rounded up to whole bags. The cheaper of the two becomes the headline.
Worked example
A 10 × 10 ft patio, 4 in thick, 10% extra, ready-mix at $165 per yard and 80 lb bags at $6.50.
- Volume with waste: 33.3 × 1.1 = 36.7 cu ft (1.36 cu yd)
- Ready-mix order: rounded up to 1.5 cu yd × $165 = $247.50
- Bags: 36.7 ÷ 0.60 = 61.1 → 62 × $6.50 = $403
- With a $60 short-load fee, ready-mix is $307.50 — still cheaper
Expect to spend about $247.50 on ready-mix, saving about $155 over bags — plus you avoid lifting 62 bags.
How much extra to allow
Order a little extra either way — running short on a pour is worse than a few leftover bags.
| Situation | Allow |
|---|---|
| Formed slab on a level base | 5% |
| Typical patio, walkway or footing | 10% |
Reading your result
The highlighted cost is the cheaper option. The 'saves' row shows the gap.
For very small pours, bags often win once the short-load fee is counted. Above about 1½ cubic yards, ready-mix nearly always does.
Remember the hidden costs of bags: a mixer rental, extra helpers and a long day.
Assumptions
- Prices are the ones you enter; the defaults are placeholders, not local prices.
- The bag count assumes standard premix yield. Pump trucks, finishing, forms and labor aren't included.
Unit conversions use exact definitions (1 in = 25.4 mm, 1 US gal = 3.785 L). See the calculation methodology for rounding rules.
When to call a professional
- Large slabs and driveways usually need a crew, a pump or chute access, and finishing skill. Ask contractors for an installed price to compare.
Frequently asked questions
Is it cheaper to buy bags or ready-mix concrete?
Bags are cheaper only for small jobs — usually under about 1 cubic yard once short-load fees are counted. Above that, ready-mix almost always costs less per yard.
What is a short-load fee?
A surcharge for orders below the plant's minimum, often 4–6 cubic yards. It can be $50–$150 or more, so always ask.
How much is a yard of concrete?
It varies by region and season. Call two local plants — the calculator uses whatever price you enter.