How to measure
- Measure length and width inside the forms.
- Choose the thickness: 4 in for patios and shed floors, 5–6 in for driveways.
- Thickened edges: enter the total edge depth (for example 8 in) and how wide the deeper band is.
- Gravel base: the compacted depth of crushed stone under the slab, usually 4 in.
- Reinforcement: a rebar grid (spacing under Advanced options) or 6 × 6 welded wire mesh.
How the concrete slab calculation works
Slab = length × width × thickness Thickened edge = (L × W − (L − 2e)(W − 2e)) × (edge depth − thickness) Concrete order = (slab + edge) × (1 + waste) Gravel order = L × W × gravel depth × 1.15, at 1.4 tons per cu yd Rebar = bars each way at spacing, 3 in from edges, + 10% laps ÷ 20 ft Mesh sheets = area ÷ (4.5 × 9.5 ft net per 5 × 10 sheet)
The slab is a box: length × width × thickness. A thickened edge adds a ring of extra depth around the perimeter, measured as the band width e times the depth beyond the slab.
Gravel is ordered 15% over its compacted volume because loose stone compacts. Rebar runs both ways at the chosen spacing, kept 3 in in from the forms, with 10% added for lap splices.
Worked example
A 12 × 10 ft shed slab, 4 in thick, on 4 in of gravel, with a #4 rebar grid at 18 in and 10% extra concrete.
- Concrete: 12 × 10 × 0.333 = 40 cu ft; with 10% waste: 44 cu ft (1.63 cu yd)
- Order: 1.75 cu yd of ready-mix, or 44 ÷ 0.6 = 73.3 → 74 × 80 lb bags
- Gravel: 40 cu ft = 1.48 cu yd × 1.15 = 1.70 cu yd ≈ 2.39 tons
- Rebar: 7 bars × 11.5 ft + 8 bars × 9.5 ft = 156.5 ft × 1.1 = 172 ft → 9 × 20 ft bars
Order 1.75 cubic yards of concrete, about 2.4 tons of gravel and nine 20 ft #4 bars. At $165/yd, $45/ton and $9/bar that's about $477 in materials.
How much extra to allow
Concrete waste covers uneven subgrade, form bowing and what's left in the chute. Running short leaves a cold joint.
| Situation | Allow |
|---|---|
| Formed slab on compacted, level gravel | 5% |
| Typical patio or shed slab | 10% |
| Uneven ground or hand-graded base | 10–15% |
Reading your result
The highlighted concrete row is how to buy: ready-mix above about 1½ cubic yards, bags below.
Gravel and reinforcement each have their own buy row. Gravel is sold by the ton or yard — ask which your supplier uses.
Turn on cost to see the cheaper concrete option plus gravel and steel in one material total.
Assumptions
- The subgrade is level and the forms are square. Low spots make the slab thicker and use more concrete.
- Gravel weighs about 1.4 tons per cubic yard and compacts by about 15%.
- Rebar is #4 in 20 ft lengths. Bar chairs, tie wire and form boards aren't included.
Unit conversions use exact definitions (1 in = 25.4 mm, 1 US gal = 3.785 L). See the calculation methodology for rounding rules.
When to call a professional
- Driveways, garage floors, slabs that carry walls, and anything on clay or fill need the right base, thickness and reinforcement for your soil. Get local advice or a contractor quote.
Frequently asked questions
How thick should a concrete slab be?
4 in for patios, walkways and shed floors; 5–6 in for driveways and garage floors. Add thickened edges under walls or where vehicles cross the edge.
How much gravel do I need under a slab?
Usually 4 in compacted. For a 12 × 10 ft slab that's about 1.7 cubic yards (2.4 tons) once compaction is allowed for.
Rebar or wire mesh?
Rebar holds cracks tighter and is easier to keep in the middle of the slab. Mesh is quicker for thin patios. Either only works if it's lifted into the slab, not left on the gravel.
How much concrete for a 12 × 12 slab?
At 4 in thick, 48 cu ft or 1.78 cubic yards; with 10% extra about 1.96 yards, so order 2 yards.