Skip to content
MeasureToBuy

Concrete Slab Calculator

Enter the slab size and thickness, and optionally thickened edges, a gravel base and reinforcement. You'll get the concrete order, the gravel to buy, and the rebar bars or mesh sheets.

Measurements

4 in for patios and sheds, 5–6 in for driveways.

Compacted crushed stone under the slab. 0 to skip.

Reinforcement

#4 (½ in) bars in a grid

Waste allowance

Covers uneven ground, form bowing and spillage. 5–10% is standard.

Advanced optionscoverage, sizes, custom values
Bag size

0.60 cu ft per bag

Your estimate

You need about 1.63 cubic yards of concrete.

1.48 cu yd for the slab, plus 10% waste.

Slab area
120 sq ft
Thickness
4 in
Concrete volume
1.48 cu yd
Same volume
40 cu ft
Waste allowance
10%
Volume with waste
1.63 cu yd
80 lb premix bags0.6 cu ft per bag
74 bags
Or ready-mix orderrounded up to ¼ yard
1.75 cu yd
Approximate weight
6,592 lb

Gravel base

Compacted volume+15% for compaction included below
1.48 cu yd
Order
1.7 cu yd
Approximate weightat 1.4 tons per cu yd
2.39 tons

Rebar grid

Bars running lengthwise11.5 ft each
7 bars
Bars running widthwise9.5 ft each
8 bars
Total length incl. 10% laps
172 ft
20 ft bars to buy
9 bars
  • Book ready-mix early and ask about the short-load fee for small orders.
Slab · plan and section
12 ft10 ftPLAN4 inSECTIONGRAVEL 4 in
Volume = 12 ft × 10 ft × 4 in. The section is drawn deeper than scale so thickness is visible.

Next step

Turn this into an order sheet

You need about 1.63 cu yd. The project planner adds a cost comparison and printable summary.

Start the Pour Concrete project

Also useful

Price the base separately

Gravel is sold by the ton or yard — check delivery minimums.

Gravel calculator

How to measure

  1. Measure length and width inside the forms.
  2. Choose the thickness: 4 in for patios and shed floors, 5–6 in for driveways.
  3. Thickened edges: enter the total edge depth (for example 8 in) and how wide the deeper band is.
  4. Gravel base: the compacted depth of crushed stone under the slab, usually 4 in.
  5. Reinforcement: a rebar grid (spacing under Advanced options) or 6 × 6 welded wire mesh.

How the concrete slab calculation works

Slab             = length × width × thickness
Thickened edge   = (L × W − (L − 2e)(W − 2e)) × (edge depth − thickness)
Concrete order   = (slab + edge) × (1 + waste)
Gravel order     = L × W × gravel depth × 1.15, at 1.4 tons per cu yd
Rebar            = bars each way at spacing, 3 in from edges, + 10% laps ÷ 20 ft
Mesh sheets      = area ÷ (4.5 × 9.5 ft net per 5 × 10 sheet)

The slab is a box: length × width × thickness. A thickened edge adds a ring of extra depth around the perimeter, measured as the band width e times the depth beyond the slab.

Gravel is ordered 15% over its compacted volume because loose stone compacts. Rebar runs both ways at the chosen spacing, kept 3 in in from the forms, with 10% added for lap splices.

Worked example

A 12 × 10 ft shed slab, 4 in thick, on 4 in of gravel, with a #4 rebar grid at 18 in and 10% extra concrete.

  1. Concrete: 12 × 10 × 0.333 = 40 cu ft; with 10% waste: 44 cu ft (1.63 cu yd)
  2. Order: 1.75 cu yd of ready-mix, or 44 ÷ 0.6 = 73.3 → 74 × 80 lb bags
  3. Gravel: 40 cu ft = 1.48 cu yd × 1.15 = 1.70 cu yd ≈ 2.39 tons
  4. Rebar: 7 bars × 11.5 ft + 8 bars × 9.5 ft = 156.5 ft × 1.1 = 172 ft → 9 × 20 ft bars

Order 1.75 cubic yards of concrete, about 2.4 tons of gravel and nine 20 ft #4 bars. At $165/yd, $45/ton and $9/bar that's about $477 in materials.

How much extra to allow

Concrete waste covers uneven subgrade, form bowing and what's left in the chute. Running short leaves a cold joint.

SituationAllow
Formed slab on compacted, level gravel5%
Typical patio or shed slab10%
Uneven ground or hand-graded base10–15%

Reading your result

The highlighted concrete row is how to buy: ready-mix above about 1½ cubic yards, bags below.

Gravel and reinforcement each have their own buy row. Gravel is sold by the ton or yard — ask which your supplier uses.

Turn on cost to see the cheaper concrete option plus gravel and steel in one material total.

Assumptions

  • The subgrade is level and the forms are square. Low spots make the slab thicker and use more concrete.
  • Gravel weighs about 1.4 tons per cubic yard and compacts by about 15%.
  • Rebar is #4 in 20 ft lengths. Bar chairs, tie wire and form boards aren't included.

Unit conversions use exact definitions (1 in = 25.4 mm, 1 US gal = 3.785 L). See the calculation methodology for rounding rules.

When to call a professional

  • Driveways, garage floors, slabs that carry walls, and anything on clay or fill need the right base, thickness and reinforcement for your soil. Get local advice or a contractor quote.

Frequently asked questions

How thick should a concrete slab be?

4 in for patios, walkways and shed floors; 5–6 in for driveways and garage floors. Add thickened edges under walls or where vehicles cross the edge.

How much gravel do I need under a slab?

Usually 4 in compacted. For a 12 × 10 ft slab that's about 1.7 cubic yards (2.4 tons) once compaction is allowed for.

Rebar or wire mesh?

Rebar holds cracks tighter and is easier to keep in the middle of the slab. Mesh is quicker for thin patios. Either only works if it's lifted into the slab, not left on the gravel.

How much concrete for a 12 × 12 slab?

At 4 in thick, 48 cu ft or 1.78 cubic yards; with 10% extra about 1.96 yards, so order 2 yards.

More concrete & masonry calculators

All concrete & masonry