Cement Calculator

Mixing concrete on site from bulk materials? Enter the volume and mix ratio to get bags of Portland cement, sand and gravel in cubic yards and tons, and roughly how much water to add.

Measurements

How will you enter it?
Mix ratio (cement : sand : gravel)

General purpose, ≈ 3,000 psi — slabs, paths

Waste allowance

Covers uneven ground, form bowing and spillage. 5–10% is standard.

Your estimate

You need 10 94 lb bags of Portland cement.

1.36 cu yd of concrete with waste, × 1.54 for dry materials, split 1 : 2 : 3.

Concrete volume
1.23 cu yd
Waste allowance
10%
Volume with waste
1.36 cu yd
Dry volume factordry materials shrink when wet
1.54 ×
Dry material volume
2.09 cu yd
94 lb bags of Portland cement1 cu ft per bag
10 bags
Water, approximatelywater–cement ratio 0.5 by weight
53 gal

Sand and gravel

Sand19 cu ft
0.7 cu yd
Sand by weight≈ 1.35 tons per cu yd
0.94 tons
Gravel28 cu ft
1.05 cu yd
Gravel by weight≈ 1.4 tons per cu yd
1.46 tons
  • This is for mixing concrete yourself from bulk cement, sand and gravel. For small jobs, premixed bags are simpler; above about 1½ cu yd, ready-mix is usually cheaper and more consistent.
  • Add water gradually — damp sand already carries some. Less water makes stronger concrete; aim for a stiff, workable mix.
Slab · plan and section
10 ft10 ftPLAN4 inSECTION
Volume = 10 ft × 10 ft × 4 in. The section is drawn deeper than scale so thickness is visible.

Next step

Compare with premix bags

Premixed bags cost more per yard but skip the measuring and mixing.

Concrete Bag Calculator

Also useful

Order the sand

Check the sand order against your supplier's minimum.

Sand Calculator

How to measure

  1. Measure length, width and thickness of the pour, or enter a volume you already know.
  2. Pick a mix ratio by volume: cement : sand : gravel. 1 : 2 : 3 is a good general-purpose mix.
  3. Check the bag weight. US Portland cement comes in 94 lb bags (1 cu ft); metric bags are usually 25 kg.

How the cement calculation works

Wet volume   = length × width × thickness
Dry volume   = wet volume × (1 + waste) × 1.54
Cement       = dry volume × 1 ÷ (sum of ratio parts)
Sand, gravel = dry volume × their parts ÷ (sum of parts)
Tons         = cu yd × 1.35 (sand) or 1.4 (gravel)
Water        ≈ cement weight × 0.5

Loose cement, sand and gravel shrink by about a third when water is added: sand fills the gaps between stones, and cement fills the gaps between sand grains. Multiplying the finished volume by 1.54 gives the dry volume to buy.

The dry volume is then split by the ratio. For 1 : 2 : 3, there are six parts — one is cement, two are sand, three are gravel. A US bag of cement is 1 cu ft; metric bags are converted at 1,440 kg/m³.

Water is set by a water–cement ratio of 0.5 by weight — half a pound of water per pound of cement. Damp sand already carries water, so add it gradually.

Worked example

A 10 × 10 ft pad, 4 in thick, mixed at 1 : 2 : 3 with 10% extra.

  1. Wet volume: 10 × 10 × 0.333 = 33.3 cu ft; with 10% waste: 36.7 cu ft
  2. Dry volume: 36.7 × 1.54 = 56.5 cu ft
  3. Cement: 56.5 ÷ 6 = 9.4 cu ft → 10 × 94 lb bags
  4. Sand: 56.5 × 2 ÷ 6 = 18.8 cu ft = 0.70 cu yd ≈ 0.94 tons
  5. Gravel: 56.5 × 3 ÷ 6 = 28.2 cu ft = 1.05 cu yd ≈ 1.46 tons
  6. Water: 9.4 × 94 lb × 0.5 = 442 lb ≈ 53 gal

Buy 10 bags of Portland cement, about 0.94 tons of sand and 1.46 tons of gravel, and plan on roughly 53 gallons of water.

How much extra to allow

Some cement and aggregate is always lost to spills, the mixer drum and an uneven base.

SituationAllow
Formed pad on a level base5%
Typical site mixing10%

Reading your result

The headline is the cement to buy. Sand and gravel are shown by volume and weight — suppliers sell by one or the other, so use whichever they quote.

If you end up needing more than about 1½ cubic yards, hand mixing becomes a long day. A ready-mix truck is usually cheaper at that point.

Assumptions

  • Dry volume factor of 1.54, the usual site allowance (textbook values run 1.52–1.57).
  • Sand weighs about 1.35 tons per cu yd and gravel about 1.4 tons per cu yd when loose. Wet material weighs more.
  • Strength figures (about 3,000 psi for 1 : 2 : 3) assume clean aggregate, correct water and proper curing. Site mixes vary.

Unit conversions use exact definitions (1 in = 25.4 mm, 1 US gal = 3.785 L). See the calculation methodology for rounding rules.

When to call a professional

  • Structural concrete — footings, foundations, beams — should use a specified mix, often ready-mix with a delivery ticket. Ask your engineer or building department.

Frequently asked questions

How many bags of cement in a cubic yard of concrete?

About 7 bags of 94 lb Portland cement for a 1 : 2 : 3 mix: 27 cu ft × 1.54 = 41.6 cu ft dry ÷ 6 parts = 6.9 cu ft of cement.

What is the best concrete mix ratio?

1 : 2 : 3 (cement : sand : gravel) is a reliable general-purpose mix for slabs and paths. Use 1 : 2 : 4 for mass footings and 1 : 1.5 : 3 where you need more strength.

Why multiply by 1.54?

Dry materials pack together when mixed with water, so the finished concrete takes up about two-thirds of the loose volume. 1.54 converts finished volume back to the dry material you need.

Is cement the same as concrete?

No. Cement is the binder; concrete is cement plus sand, gravel and water. For premixed bags, use the Concrete Bag Calculator instead.

More concrete & masonry calculators

All concrete & masonry