Concrete Order Worksheet
MeasureToBuyProject / site address
Pour date
Volume
| Item (slab, footing, steps…) | Length (ft) | Width (ft) | Depth (ft) | Qty | Cu ft (L × W × D × qty) |
|---|---|---|---|---|---|
Order
Total cu ft
÷ 27 = cu yd
× (1 + waste, usually 5–10%)
Ready-mix order (round up to ¼ yd)
Or 80 lb bags (cu ft ÷ 0.60)
Or 60 lb bags (cu ft ÷ 0.45)
For the supplier
Mix / strength specified
Delivery time window
Truck access & distance to pour
Pump or chute needed?
Short-load / minimum fee
Supplier & phone
Formulas
Slab or footing = length × width × thickness (inches ÷ 12 = feet) Cubic yards = cubic feet ÷ 27 Bags = cubic feet ÷ bag yield (80 lb ≈ 0.60 cu ft, 60 lb ≈ 0.45, 40 lb ≈ 0.30)